Additional maintenance works on runway 25L/07R

Works

Following the first phase of maintenance works on runway  25L/07R last June, the second and final phase will take place in November. 

Following maintenance works on the central part of runway 25L/07R in June, it was decided to renovate the remaining parts of the runway after further inspection. The works are being carried out to continue to ensure safe and smooth operations, particularly in view of the upcoming winter season. 

A detailed schedule for these additional works is currently being established in consultation with skeyes and the partners at the airport, taking into account the flight schedules. The maintenance is being planned in such a way to minimise the impact on operations. The actual works will start on 6 November and are scheduled for completion on 12 November, with a possible delay of a few days in case of bad weather.

As it intersects with runway 25L/07R, runway 01/19 will have to close for 48 hours to allow for the planned work. 

The works will have an impact on runway use, which means that it will not always be possible to apply the PRS ( Preferential Runway System ). 

Runway use, wind conditions, any planned works and the potential impact on runway use are always announced on this website.

Related articles

Renovation of key taxiway intersection to start on 2 March 2026

Works

From 2 March to 19 September 2026, Brussels Airport will carry out major renovation works at a key taxiway intersection leading to the primary runway 07L/25R. These works are essential to ensure the continued safety and reliability of air traffic operations. The renovation is not expected to have an impact on the PRS (Preferential Runway System).

Read more

Renovation of runway 07R/25L scheduled from 12 July to 27 August

Works

Brussels Airport will carry out major renovation works on runway 07R/25L from 12 July to 27 August 2025 to ensure safe and reliable air traffic operations. The renovation will include fresh asphalt, new runway lights and improvements to the sewerage system for better drainage.

Read more

Renovation of runway 07R/25L during the summer holidays

Works

From 12 July to 27 August 2025, Brussels Airport will be renovating runway 07R/25L. The works are necessary to continue to guarantee safe air traffic. The runway will undergo extensive renovation, including new asphalt, new runway lights and new sewerage to improve runway drainage, and will be closed to air traffic for the entire duration.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right