Work on taxiway Z completed 1 day ahead of schedule
The two upper asphalt layers of taxiway Z (behind aprons 40 and 4, near the Brussels Airlines and TUI fly hangars) were demolished and replaced. We are talking about a surface area of 50,000m².
New sewers were installed over a length of 710 meters and the taxiway lights were replaced with LED lamps.
Today, the markings were completed.
Taxiway Z is now operational again, one day ahead of schedule.
Related articles
Renovation of runway 07L/25R at Brussels Airport completed this weekend
The renovation works on runway 07L/25R at Brussels Airport and the final tests will be completed on the 23rd of August at 6 am, at which time the runway will be taken into use again.
Renovation runway 07L/25R: preliminary works from 8 July until 13 July
The preliminary works will commence on 8 July at 3.30 pm and are scheduled to end on 13 July at 5 am, after which the actual renovation work on runway 07L/25R will start.
Renovation of runway 07L/25R at Brussels Airport during the summer holiday
From 13 July to 23 August, Brussels Airport will be renovating runway 07L/25R under strict observance of COVID-19 measures.