Events with impact on the PRS – 15/06/2019

Works

Description and indicative timing

 Saturday 15 June from 1 pm to 8 pm:

  • Removal of rubber deposit TDZ 25L and TDZ 01

 Saturday 15 June from 1 pm to 11 pm:

  • Maintenance and light measurements on runways 07/25R and 01/19

Closed runway

 On Saturday 15 June from 1 pm to 11 pm:

  • runway 07L/25R and 01/19 closed

Runway use during the works

 On Saturday 15 June from 1 pm to 11 pm:

  • take-off on runway 25R
  • landing on runway    25R

Remarks

 

  • On the morning of the day the works are scheduled, it will be decided based on the weather forecast whether the works will actually be carried out. The timing of the works also depends on how busy operations at the airport are.
  • Between the end of the rubber removal works and maintenance runway lighting until light measurements runways 07/25L and 01/19 can be taken in use again.

 

Related articles

Replacement of the BUB beacon (phase 2) from 16 August until 30 September 2019

Works

In the framework of the modernisation programme of the Belgian air navigation beacon network, skeyes will shortly be proceeding with the second phase of replacing the BUB beacon, located in the community of Kortenberg, close to Brussels Airport.

Read more

Events with impact on the PRS - 28-06-2019

Works

On 28 June between 8:30 en 11:00 am maintenance works will be carried out on runway 07L/25R.

Read more

Events with impact on the PRS - 22-23/06/2019

Works

On Saturday 22 June and Sunday 23 June runway 01/19 will be closed from 10 am to 6 am to allow for the calibration of the ILS signals.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right