Events with impact on the PRS - 27-28/08/2019

Works

Description and indicative timing

From 27/08/2019 11pm to 28/08/2019 05.30 am:

  • Urgent asphalt repair on runway 07L/25R

Closed runway

From 27/08/2019 11pm to 28/08/2019 05.30 am:

  • Runway 07L/25R closed

Runway use during the works

From 27/08/2019 11pm to 28/08/2019 05.30 am:

  • Landings on runway 25L and/or runway 19
  • Take-offs from runway 19 and/or runway 25L.

Remarks

 

  • The exact time at which work will commence is coordinated between the control tower and Airport Inspection, depending on traffic.
  • If the wind conditions allow the use of a 01/07R runway configuration during the day on 27/08/2019, work may start earlier.

 

Related articles

Events with impact on the PRS - 20-21/11/2019

Works

From Wednesday 20 November 2019 at 11 pm to Thursday 21 November at 1.29 am, runways 07R/25L and 01/19 will be closed for a snow removal exercise.

Read more

Events with impact on the PRS - 15-24/11/2019

Works

In the period from Friday 15 November until Sunday 24 November, in case of east wind, repair works will be carried out on runway 07L/25R in the afternoon.

Read more

Events with impact on the PRS - 13/11/2019

Works

On Wednesday 13 November 2019, runway 07R/25L will be closed from 1.30 pm to 2.30 pm to allow for the measurements of the localizer and glide path signals of runway 25L.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right