On Wednesday 21 August 2019 from 1 pm to 3 pm:

  • Measurement of the localizer signal of runway 25L

Closed runway

On Wednesday 21 August 2019 from 1 pm to 3 pm:

  • Runway 07R/25L closed

Runway use during the measurements

On Wednesday 21 August 2019 from 1 pm to 3 pm:

  • Landing on runway 25R
  • Take-off from runway 25R and, if necessary, runway 19

Impact on the preferential runway use

On Wednesday 21 August 2019 from 1 pm to 3 pm:

  • The landings that under normal conditions take place on runway 25L will move to runway 25R

Remarks

 

  • The measurements will not be carried out if the runway configuration in use is 01/07 or 07/07.
  • The exact timing of the 30 minutes required for the measurements will be determined in close consultation between ATC (skeyes) and Airport Inspection (Brussels Airport Company.

 

Related articles

Events with impact on the PRS - 16/09/2019

Works

On Monday 16 September 2019, runway 07R/25L will be closed from 1 pm to 5 pm for runway marking works.

Read more

Event with impact on the PRS - 14-15/09/2019

Works

UPDATE: The works on runway 07R/25L scheduled for Saturday 14 September 12 noon to Sunday 15 September 6 am are postponed.

Read more

Events with impact on the PRS - 07-08/09/2019

Works

From Saturday 7 September 2019 at 12:00 noon to Sunday 8 September 05:59 am runways 01/19 and 07R/25L will be closed for maintenance.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right