Events with impact on the PRS - 1 June 2019

Works

Description and indicative timing

On Saturday 1 June 2019 from 1 pm to 6 pm:

  • Wildlife hazard management works

Closed runway

from 1 pm to 6 pm:

  • Runway 07L/25R closed

Planned runway usage during the works

from 1 pm to 6 pm:

  • Landings on runway 25L and/or runway 19
  • Take-offs on runway 19 and/or 25L

Impact on the application of the PRS

from 1 pm to 6 pm:

  • Landings that under normal conditions take place on runway 25R will move to runway 25L and/or 19
  • Take-offs that under normal conditions take place on runway 25R will move to runway 19 and/or runway 25L

Remarks

On the eve of the planned works, it will be decided after the 4pm meteo briefing whether the works will actually be carried out.  

Related articles

Events with impact on the PRS - 11/12/2019

Works

Wednesday 11 December, runway 07R/25L will be closed from 12.10 pm to 12.40 pm for measurements by a land surveyor.

Read more

Events with impact op het PRS - 10/12/2019

Works

UPDATE: On Tuesday 10 October from 2:00 pm to 3:00 pm, runway 07R/25L will be closed to allow for the measurements of the ILS signals of runway 25L.

Read more

Events with impact on the PRS - 24/11/2019

Works

On Sunday 24 November, runway 01/19 will be closed from 12:00 noon to 6 pm for ILS calibration.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right